MASTER PLAN
ARTIFICIAL RECHARGE SCHEME FOR THE YEAR 2008-09
ABSTRACT
PROGRESS AS ON
12.08.2008
|
| Sl
No |
Name of
Department
|
Alloted
Amount in Crores
|
Amount for
which Administrative Sanction has been obtained from the Govt. in Crores
|
Balance
Amount for which Administrative Sanction has to be obtained from the Govt.
in Crores.
|
| 1 |
WRO |
48 |
30.0503 |
17.9497 |
| 2 |
SG
&SWRDC |
2 |
0.8218 |
1.1782 |
| 3 |
TWAD |
24 |
19.2357 |
4.7643 |
| 4 |
FOREST |
1 |
Nil |
1 |
| 5 |
Agricultural
Engineering |
25 |
Nil |
25 |
| |
Total |
100 |
50.1078 |
49.8922 |
1.
DEPARTMENT : WRO
| G.O
Ref |
Year |
Alloted
Full Amount for all the schemes in Crores |
Value
of Amount for which Administrative Sanction obtained
in Crores |
Balance
Amount for which sanction has to be obtained in crores |
| G.O
MS No 198, PW(R2)D dt 10.6.2008 |
2008-09 |
48 |
|
|
| G.O
MS No 242, PW(R2)D dt 5.8.2008 |
2008-09 |
|
4.164 |
|
| G.O
MS No 243, PW(R2)D dt 5.8.2008 |
2008-09 |
|
24.6123 |
|
| G.O
MS No 245, PW(R2)D dt 5.8.2008 |
2008-09 |
|
1.274 |
|
| |
Total |
48 |
30.0503 |
17.9497 |
| |
Estimate
for which Designs are being evolved by S.E. (Designs) |
20.67 |
| |
Value
of Schemes in the Master List that can not be taken up |
1.549 |
2.
DEPARTMENT : SG&SWRDC
| Period |
|
|
As
on 12-8-2008 |
| G.O
Ref |
Year |
Alloted
Full Amount for all the schemes in Lakhs |
Value
of Amount for which Administrative Sanction obtained
in Lakhs |
Balance
Amount for which sanction has to be obtained
in Lakhs |
| G.O
MS No 198, PW(R2)D dt 10.6.2008 |
2008-09 |
200 |
|
|
| G.O
MS No 244, PW(R2)D dt 5.8.2008 |
2008-09 |
|
82.18 |
|
| |
Total |
200 |
82.18 |
117.82 |
| |
Value
of Estimates Sent to Govt by
C.E(PF) |
185.71 |
3.
DEPARTMENT : TWAD
| Period |
|
|
As
on 12-8-2008 |
| G.O
Ref |
Year |
Alloted
Full Amount for all the schemes in Crores |
Value
of amount for which Administrative Sanction obtained in Crores |
Balance
Amount for which sanction has to be obtained in Crores |
| G.O
MS No 198, PW(R2)D dt 10.6.2008 |
2008-09 |
24 |
|
|
| |
2008-09 |
|
19.2357 |
|
| |
Total |
24 |
19.2357 |
4.7643 |
| Note |
Value
of Schemes to be sanctioned |
4.7643 |
4.
DEPARTMENT : FOREST
| Period |
|
|
As
on 12-8-2008 |
| G.O
Ref |
Year |
Alloted
Full Amount for all the schemes in Crores |
Value
of amount for which Administrative Sanction obtained in Crores |
Balance
Amount for which sanction has to be obtained in Crores |
| G.O
MS No 198, PW(R2)D dt 10.6.2008 |
2008-09 |
1 |
NIL |
1 |
| Note |
Value
of Schemes Sent to Govt for obtaining the Administrative Sanction |
1
Crore |
| Reason
for delay |
The
proposals sent by the Forest Department has been returned for attending
some remarks. |
5.
DEPARTMENT : AGRICULTURAL
ENGINEERING
| Period |
|
|
As
on 12-8-2008 |
| G.O
Ref |
Year |
Alloted
Full Amount for all the schemes in Crores |
Value
of amount for which Administrative Sanction obtained in Crores |
Balance
Amount for which sanction has to be obtained
in Crores |
| G.O
MS No 198, PW(R2)D dt 10.6.2008 |
2008-09 |
25 |
NIL |
25 |
| Note |
Value
of Schemes Sent to Govt for obtaining the Administrative Sanction |
25
Crores |
| Reason
for delay |
As
per the enquiry from the Agricultural Engineering department the
Administrative Sanction is awaited from the Govt. |