MASTER PLAN ARTIFICIAL RECHARGE SCHEME FOR THE YEAR  2008-09

                                                        ABSTRACT

PROGRESS AS ON 12.08.2008

Sl No

Name of Department

Alloted Amount in Crores

Amount for which Administrative Sanction has been obtained from the Govt. in Crores

Balance Amount for which Administrative Sanction has to be obtained from the Govt. in Crores.

1 WRO 48 30.0503 17.9497
2 SG &SWRDC 2 0.8218 1.1782
3 TWAD 24 19.2357 4.7643
4 FOREST 1 Nil 1
5 Agricultural Engineering 25 Nil 25
  Total 100 50.1078 49.8922

 

1.  DEPARTMENT   : WRO

G.O Ref Year Alloted  Full Amount for all the schemes in Crores Value of Amount for which Administrative Sanction obtained  in Crores Balance Amount for which sanction has to be obtained in crores
G.O MS No 198, PW(R2)D dt 10.6.2008 2008-09 48    
G.O MS No 242, PW(R2)D dt 5.8.2008 2008-09   4.164  
G.O MS No 243, PW(R2)D dt 5.8.2008 2008-09   24.6123  
G.O MS No 245, PW(R2)D dt 5.8.2008 2008-09   1.274  
  Total 48 30.0503 17.9497
 Note Estimate for which Designs are being evolved by S.E. (Designs) 20.67
  Value of Schemes in the Master List that can not be taken up 1.549

2.  DEPARTMENT   : SG&SWRDC

Period     As on  12-8-2008
G.O Ref Year Alloted  Full Amount for all the schemes in Lakhs Value of Amount for which Administrative Sanction obtained  in Lakhs Balance Amount for which sanction has to be obtained  in Lakhs
G.O MS No 198, PW(R2)D dt 10.6.2008 2008-09 200    
G.O MS No 244, PW(R2)D dt 5.8.2008 2008-09   82.18  
  Total 200 82.18 117.82
 Note Value of Estimates Sent to Govt  by C.E(PF) 185.71

3.  DEPARTMENT   : TWAD

Period     As on  12-8-2008
G.O Ref Year Alloted  Full Amount for all the schemes in Crores Value of amount for which Administrative Sanction obtained in Crores Balance Amount for which sanction has to be obtained in Crores
G.O MS No 198, PW(R2)D dt 10.6.2008 2008-09 24    
  2008-09   19.2357  
  Total 24 19.2357 4.7643
Note Value of Schemes to be sanctioned 4.7643

4.  DEPARTMENT   : FOREST

Period     As on  12-8-2008
G.O Ref Year Alloted  Full Amount for all the schemes in Crores Value of amount for which Administrative Sanction obtained in Crores Balance Amount for which sanction has to be obtained in Crores
G.O MS No 198, PW(R2)D dt 10.6.2008 2008-09 1 NIL 1
Note Value of Schemes Sent to Govt for obtaining the Administrative Sanction 1 Crore
Reason for delay The proposals sent by the Forest Department has been returned for attending some remarks.

5.  DEPARTMENT   : AGRICULTURAL ENGINEERING

Period     As on  12-8-2008
G.O Ref Year Alloted  Full Amount for all the schemes in Crores Value of amount for which Administrative Sanction obtained in Crores Balance Amount for which sanction has to be obtained  in Crores
G.O MS No 198, PW(R2)D dt 10.6.2008 2008-09 25 NIL 25
Note Value of Schemes Sent to Govt for obtaining the Administrative Sanction 25 Crores
Reason for delay As per the enquiry from the Agricultural Engineering department the Administrative Sanction is awaited from the Govt.