MASTER PLAN ARTIFICIAL RECHARGE SCHEME FOR  2008-09

Name  of Department  : Chennai Region, WRD                                                 Progress up to the period : Oct '08

Sl No Location of the Artificial Recharge  Structure. No of works Estimate Cost in Lakhs G.O Ref Present Stage of work. Remarks
1 Tiruvallore district 1 work 744 GO Ms No 321 Pw(R2)Dep dt 3.11.2008. G.O just receieved and the work will be started soon.  
2 Krishnagiri district. 1 work 38.33 GO Ms No 243 Pw(R2)Dep dt 5.8.2008. Tender receieved on 17.10.2008 and the agency to be decided.  
3 Dharmapuri district. 5 work 151 GO Ms No 243 Pw(R2)Dep dt 5.8.2008. Work is under progress 10 % work completed.
  Dharmapuri district. 2 work 88.65 GO Ms No 243 Pw(R2)Dep dt 5.8.2008. Tender finalised and the work to be started.  
  Dharmapuri district. 1 work 115.33 GO Ms No 291 Pw(R2)Dep dt 22.9.2008. Tender to be called  
4 Villupuram district 1 work 12.5 GO Ms No 243 Pw(R2)Dep dt 5.8.2008. Work under progress. 40 % work completed.
5 Cuddalore district. 1 work 20.7 GO Ms No 243 Pw(R2)Dep dt 5.8.2008. Work under progress. 30 % work completed.
  Cuddalore district. 1 work 103.5 Individual GO awaited. A.S awaited. Estimate sent to Government.
  Cuddalore district. 1 work 550 Individual GO awaited. A.S awaited. Estimate sent to SE designs for vetting.

Name  of Department  : Madurai Region, WRD                                                 Progress up to the period : Oct '08

Sl No Location of the Artificial Recharge  Structure. No of works Estimate Cost in Lakhs G.O Ref Present Stage of work with percentage of physical progress Remarks
1 Madurai district 2 work 79.5 GO Ms No 243 Pw(R2)Dep dt 5.8.2008. Tender receieved and is under finalaisation.  
2 Dindukal district 3 work 82 GO Ms No 243 Pw(R2)Dep dt 5.8.2008. Tender receieved and is under finalaisation.  
3 Theni district 6 work 384.2 GO Ms No 243 Pw(R2)Dep dt 5.8.2008. Tender receieved and is under finalaisation.  
4 Virudunagar district 1 work 27 GO Ms No 243 Pw(R2)Dep dt 5.8.2008. Work under progress.  
5 Tirunelveli district. 3 work 103 GO Ms No 242 Pw(R2)Dep dt 5.8.2008. Work under progress.  
6 Thoothukudi district. 3 work 164 GO Ms No 243 Pw(R2)Dep dt 5.8.2008. Work under progress.  

Name  of Department  : Pollachi Region, WRD                                                 Progress up to the period : Oct '08

Sl No Location of the Artificial Recharge  Structure. No of works Estimate Cost in Lakhs G.O Ref Present Stage of work with percentage of physical progress Remarks
1 Erode district 14  work 313.4 GO Ms No 242 Pw(R2)Dep dt 5.8.2008. Tender finalised and the work  just started.  
  Erode district 4 work 197.81 GO Ms No 242 Pw(R2)Dep dt 5.8.2008. Tender finalised and the work  just started.  
2 Coimbatore district 5 work 75.45 GO Ms No 243 Pw(R2)Dep dt 5.8.2008. 30 % of the work over  
  Coimbatore district 4 work 182.35 GO Ms No 243 Pw(R2)Dep dt 5.8.2008. Tender accepted and work just started  
  Coimbatore district 2 work 60 GO Ms No 243 Pw(R2)Dep dt 5.8.2008. Alternate site selected and estimate revised  
3 Dindukal district 1 work 27 GO Ms No 294 Pw(R2)Dep dt 29.9.2008. Tender to be called  

Name  of Department  : Tiruchy Region, WRD                                                 Progress up to the period : Oct '08

Sl No Location of the Artificial Recharge  Structure. No of works Estimate Cost in Lakhs G.O Ref Present Stage of work with percentage of physical progress Remarks
1 Salem district. 8 work 193.36 GO Ms No 243 Pw(R2)Dep dt 5.8.2008. Tenders receieved on 15.10.2008 and to be finalalised.  
2 Namakkal district 1 work 17.75 GO Ms No 243 Pw(R2)Dep dt 5.8.2008. Tenders receieved on 15.10.2008 and to be finalalised.  
3 Trichy district 11 work 207.3 GO Ms No 243 Pw(R2)Dep dt 5.8.2008. Work is under progress 40 % work completed.
  Trichy district 6 work 74.9 GO Ms No 243 Pw(R2)Dep dt 5.8.2008. Tender finalised and the work to be started.  
  Trichy district 1 work 127.4 GO Ms No 245 Pw(R2)Dep dt 22.9.2008. Tender Under scrutiny.  
4 Perambalur district. 11 work 219.26 GO Ms No 243 Pw(R2)Dep dt 5.8.2008. Work under progress. Tender finalised and work to be started.
  Perambalur district. 2 work 41.47 GO Ms No 243 Pw(R2)Dep dt 5.8.2008. Work under progress. 30 % work completed.

 

Name  of Department  : SG&SWRDC, WRD                                                 Progress up to the period : Oct '08

Sl No Location of the Artificial Recharge  Structure. No of works Estimate Cost G.O Ref Present Stage of work with percentage of physical progress Remarks
1 Pudukottai district 8 work 39.63 GO Ms No 244 Pw(R2)Dep dt 5.8.2008. work under progress.  
2 Tiruvannamalai district 3 work 30 GO Ms No 244 Pw(R2)Dep dt 5.8.2008. Tender finalised and the work is to be started.  
  Tiruvannamalai district 1 work 12.5 GO Ms No 244 Pw(R2)Dep dt 5.8.2008. Tender to be revised.  
3 Tiruvallore district. 2 work 14.28 GO Ms No 308 Pw(R2)Dep dt15.10.2008. The detailed estimate and plans are under preperation in division office.  
4 Thanjavur distrcit. 50 work 103.53 GO Ms No 305 Pw(R2)Dep dt 15.10.2008. The detailed estimate and plans are under preperation in division office.  

Name  of Department  : TWAD BOARD                                                 Progress up to the period : Oct '08


Sl No

Location of the Artificial Recharge  Structure. No of works Estimate Cost in lakhs G.O Ref Present Stage of Work Remarks
1 20 districts. 495 works 2400 MA & WS Dep GO NO 219 dt 28.5.2008. 108 work completed Expenditure incured is Rs 284 Lakhs

Name  of Department  :  Agricultural Engineering Dept                                        Progress up to the period : Oct '08

Sl No Location of the Artificial Recharge  Structure. No of works No of works Estimate Cost in Lakhs GO Ref Present Stage of work with percentage of physical progress Remarks
1 30 districts  Minor Check Dams 284 85.2 GO Ms No 299 Agriculture(AE 2) dept dt 26.9.2008. 269 works are under progress.  
2 30 districts Medium check dams 471 353.25
3 30 districts Major Check dams 501 501
4 30 districts Percolation pond with recharge shaft 167 542.75
5 30 districts Farm ponds 1093 546.5
6 30 districts Village Tanks 197 295.5
7 30 districts Recharge shafts 586 175.8  
    Total 3299 2500

Name  of Department  :  Forest Department                                        Progress up to the period : Oct '08

Sl No Location of the Artificial Recharge  Structure(Name of District,Block and Village) Nature of Artificial Recharge Structure Estimate Cost in Lakhs Present Stage of work with percentage of physical progress Remarks
1 Dindugal district Construction of Gully Plugging 5000 meter cube 26.5 As  the GO has been receieved only on the 4 th week of october-2008, the work will be started soon. Administrative Sanction receieved as per GO(D),No 301 ENVIRONMENT AND FOREST(FR7) DEPARTMENT Dt.  22-10-2008.
  Dindugal district Check Dam-7 No 14
  Dindugal district Percolation Pond-5 No 12.5
2 Krishnagiri district Check Dam-1 No 2.5
  Krishnagiri district Percolation Pond-1No 2
3 Theni district Check Dam-27 No 18.92
  Theni district Percolatin Pond-6 No 8.5
  Theni district Contour Trenches 1616.3126 meter cube 0.79
  Theni district Nulla Bunds 1505.56 RM 21.79
    Total 100  